Q85
In which step of the project method, the resources, timelines and budget for the project are identified?
- (1) Selection
- (2) Planning
- (3) Execution
- (4) Evaluation
In which step of the project method, the resources, timelines and budget for the project are identified?
CBSE answer: (2)
Answer: (2) Planning
Trap: selection only chooses the project; execution carries out the plan already made.