UPSC Prelims 2023 CSAT, question 20

Topic: Arithmetic

Q20

A,B,CA,B,C working independently can do a piece of work in 8, 16 and 12 days respectively. AA alone works on Monday, BB alone works on Tuesday, CC alone works on Wednesday; AA alone, again works on Thursday and so on. Consider the following statements :

  1. The work will be finished on Thursday.

  2. The work will be finished in 10 days.

Which of the above statements is/are correct ?

  1. (a) 1 onlyCorrect answer
  2. (b) 2 only
  3. (c) Both 1 and 2
  4. (d) Neither 1 nor 2

Solution.

Answer: (a) 1 only

  1. Taking the total work as LCM(8,16,12)=48\text{LCM}(8, 16, 12) = 48 units, the daily outputs are A=6A = 6 units, B=3B = 3 units and C=4C = 4 units, so each 3-day cycle (A,B,CA, B, C) completes 6+3+4=136 + 3 + 4 = 13 units.
  2. After 33 cycles (99 days, ending on the second Tuesday), 3×13=393 \times 13 = 39 units are done; on Day 1010 (Wednesday), AA completes 66 units (4545 units total), and on Day 1111 (Thursday), BB completes the remaining 33 units (4848 units total).
  3. Thus Statement 1 is correct (the work finishes on Thursday) and Statement 2 is incorrect (it takes 1111 days, not 1010 days).