Q57
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
- (a) 30 days
- (b) More than 30 days
- (c) Less than 30 days or more than 30 days
- (d) Data is inadequate to draw any conclusion
24 men and 12 women can do a piece of work in 30 days. In how many days can 12 men and 24 women do the same piece of work?
Answer: (d) Data is inadequate to draw any conclusion