Q80

A man completes 7/87/8 of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50% ?

  1. (a) 24
  2. (b) 21
  3. (c) 18
  4. (d) 15Correct answer

Solution.

Answer: (d) 15

  1. Completing 78\frac{7}{8} of the original job in 2121 days means the man completes 7/821=124\frac{7/8}{21} = \frac{1}{24} of the original job per day.
  2. When the total quantum of work is increased by 50%50\% (from 11 to 1.5=1281.5 = \frac{12}{8} of the original job), the remaining work to be finished is 128−78=58\frac{12}{8} - \frac{7}{8} = \frac{5}{8} of the original job.
  3. At the rate of 124\frac{1}{24} job per day, finishing the remaining 58\frac{5}{8} job takes 5/81/24=5×3=15\frac{5/8}{1/24} = 5 \times 3 = 15 days.