Q80
A man completes of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50% ?
- (a) 24
- (b) 21
- (c) 18
- (d) 15
A man completes of a job in 21 days. How many more days will it take him to finish the job if quantum of work is further increased by 50% ?
Answer: (d) 15