UPSC Prelims 2020 CSAT, question 71

Topic: Arithmetic

Q71

A person XX can complete 20% of work in 8 days and another person YY can complete 25% of the same work in 6 days. If they work together, in how many days will 40% of the work be completed?

  1. (a) 6Correct answer
  2. (b) 8
  3. (c) 10
  4. (d) 12

Solution.

Answer: (a) 6

  1. Person XX completes 20%20\% of the work in 88 days, so XX's work rate is 20%8=2.5%=52%\frac{20\%}{8} = 2.5\% = \frac{5}{2}\% of the work per day.
  2. Person YY completes 25%25\% of the work in 66 days, so YY's work rate is 256%\frac{25}{6}\% of the work per day. Working together, their combined rate is 52+256=15+256=406%\frac{5}{2} + \frac{25}{6} = \frac{15 + 25}{6} = \frac{40}{6}\% per day.
  3. Thus, to complete 40%40\% of the work together, they take 40%(40/6)%/day=6\frac{40\%}{(40/6)\%\text{/day}} = 6 days.